We received a ready new 3-phase separator installed on a supporting skid.
We noticed that the funnel underneath the three drain sample points was installed in a way that is quite difficult for the operators to reach the funnel easily and to open the ball valve downstream the funnel to allow the drained/rejected samples collected in the drain header.
Could you advise on how best adjust the situation? or, shall it be kept as it is?
Please see the attached photo for more clarification.
Regards,
We received a ready new 3-phase separator installed on a supporting skid.
We noticed that the funnel underneath the three drain sample points was installed in a way that is quite difficult for the operators to reach the funnel easily and to open the ball valve downstream the funnel to allow the drained/rejected samples collected in the drain header.
Could you advise on how best adjust the situation? or, shall it be kept as it is?
Please see the attached photo for more clarification.
Regards,