Hi All,
I am working as a lead electrical field engineer on an Aluminum Smelter in Bahrain. I am an American using the British Standards for the first time, a lot to learn. The question: the site safety department is requesting the subcontractors to earth (drive earthing rods) portable gas driven concrete vibrators. The one vibrator I looked at is rated 42 Volts, .55 Amps, 200 Hz. I have researched several sites looking for vendor manuals on gas driven concrete vibrators and have not found any site discussing earthing the portable vibrators.
I would like some feed back so I can argue with safety that earthing is not required or feed back to show the subcontractors earthing is required.
Thanks,
Kurt
I am working as a lead electrical field engineer on an Aluminum Smelter in Bahrain. I am an American using the British Standards for the first time, a lot to learn. The question: the site safety department is requesting the subcontractors to earth (drive earthing rods) portable gas driven concrete vibrators. The one vibrator I looked at is rated 42 Volts, .55 Amps, 200 Hz. I have researched several sites looking for vendor manuals on gas driven concrete vibrators and have not found any site discussing earthing the portable vibrators.
I would like some feed back so I can argue with safety that earthing is not required or feed back to show the subcontractors earthing is required.
Thanks,
Kurt