Rejido
Structural
- Dec 18, 2007
- 8
Any thoughts?
Just today I found a crack line located at the mid-span of my 6-m (500mm x 700mm) RC girder. The girder was designed to be connected with a wide flange steel beam at the mid-point of it.
The connection used was a 10mm thick plate anchor bolted to the RC girder with 6pcs M20 chemical bolts.
The steel beam was then full welded to the plate.
What do you think? does the increase of temperature during welding caused the RC girder to crack? or please share if you also have the same experiences...
Just today I found a crack line located at the mid-span of my 6-m (500mm x 700mm) RC girder. The girder was designed to be connected with a wide flange steel beam at the mid-point of it.
The connection used was a 10mm thick plate anchor bolted to the RC girder with 6pcs M20 chemical bolts.
The steel beam was then full welded to the plate.
What do you think? does the increase of temperature during welding caused the RC girder to crack? or please share if you also have the same experiences...