cyphos168
Civil/Environmental
- Feb 25, 2016
- 37
Hi All,
I am currently doing a design of a 1050mm diameter contiguous bored pile wall. I have the option of using either LEM or LEM with Beam Elastoplastic foundation analysis. I have tried both with different results.
I am trying to figure out which one is best to use as the Beam elastoplastic method produces a lot of deflection and require a deeper embedment depth compared to LEM method.
The wall is installed in soft clay up to a depth of 7m of SPT varying from 4 to 8 and 4-5m into the hard clay stratum with SPT of 50 and over. The wall freestanding height is 5.4m.
Any advice is appreciated. Thanks.
Alex
I am currently doing a design of a 1050mm diameter contiguous bored pile wall. I have the option of using either LEM or LEM with Beam Elastoplastic foundation analysis. I have tried both with different results.
I am trying to figure out which one is best to use as the Beam elastoplastic method produces a lot of deflection and require a deeper embedment depth compared to LEM method.
The wall is installed in soft clay up to a depth of 7m of SPT varying from 4 to 8 and 4-5m into the hard clay stratum with SPT of 50 and over. The wall freestanding height is 5.4m.
Any advice is appreciated. Thanks.
Alex