Greetings-
I'm getting into a heat debate with my company's supply chain (s/c) department on BOM structure and ECO workflow and using Agile PLM for managment
Typical scenerio is I've been tasked with a design project. I complete the design in solidworks, then using Agile I create the BOMs, load in the pdf drawings, and make a product tree. I take great care in making sure the BOM's callouts assembly drawing and 3d CAd model match perfectly.
Next I send it out for review, using Agile again. Engineering manager reviews the documentation (basically rubber stamping it). Then supply chain reviews it and comments they want the entire documentation package restrucutred to suit their needs, basically they want either a flat level BOM, or restructure parts from one BOM to another. In addtion, they ask to remove assembly drawings becasue they only care about the detail drawings. I asked my manager about this and he said, because its easier for them to order parts if everything is flat level. But it make a mess for engineering
There are a host of issues going theat route, first off to restructure Agile BOM's means I have to reconfigure the 3d model and assembly drawings, which is labo intense. Secondly, I have sub assembly designs that are used in mnay other design with the 3d model and Agile BOM's. Its come to a Mexican stand off, where s/c will not release designs unless its restructured and I don't have the time or desire to redesign a project.
My arguement has been..So I'll design a prodcut send it out for preliminary review to s/c and then have to redesign it again.
So my question how to deal with something like this?
Regards
F
I'm getting into a heat debate with my company's supply chain (s/c) department on BOM structure and ECO workflow and using Agile PLM for managment
Typical scenerio is I've been tasked with a design project. I complete the design in solidworks, then using Agile I create the BOMs, load in the pdf drawings, and make a product tree. I take great care in making sure the BOM's callouts assembly drawing and 3d CAd model match perfectly.
Next I send it out for review, using Agile again. Engineering manager reviews the documentation (basically rubber stamping it). Then supply chain reviews it and comments they want the entire documentation package restrucutred to suit their needs, basically they want either a flat level BOM, or restructure parts from one BOM to another. In addtion, they ask to remove assembly drawings becasue they only care about the detail drawings. I asked my manager about this and he said, because its easier for them to order parts if everything is flat level. But it make a mess for engineering
There are a host of issues going theat route, first off to restructure Agile BOM's means I have to reconfigure the 3d model and assembly drawings, which is labo intense. Secondly, I have sub assembly designs that are used in mnay other design with the 3d model and Agile BOM's. Its come to a Mexican stand off, where s/c will not release designs unless its restructured and I don't have the time or desire to redesign a project.
My arguement has been..So I'll design a prodcut send it out for preliminary review to s/c and then have to redesign it again.
So my question how to deal with something like this?
Regards
F