WARose
Structural
- Mar 17, 2011
- 5,594
I've been asked to break equipment & steel erection costs out of a estimate. For steel erection, I'm use to seeing (in the southeast, for low rise buildings) around $300/ton. But for equipment....I'm not sure. It would likely vary based on needed crane size and so forth......but does anyone have a good rule of thumb they use? Thanks.