Loopee
Electrical
- Jun 8, 2006
- 27
I have worked most of my career for what is usually called A&E firms or Consultant Engineers. We make the construction drawings and develop instrument specifications for chemical process projects. Data sheets for instruments, schematics for connection to the PLC or DCS, instument location plans, wiring to cabinets and field junction boxes, and interface to equipment vendor packages are typically done in one of our projects.
The I&C (Instrumentation and Controls)discipline has lots of little things to worry about, i.e. transmitters, switches, control vavles, etc to specify. For example we might have project with an instrument list that contains 1500 instruments.
With the number of items we keep up with its natural that over time we have calculated the number of hours it takes us to do a project on a hours per instrument basis. We would count an instrument so that a valve is counted as one instrument and not count all the components associated with it- limit switches and solenoid valve, positioners, etc.
With increasing competition squeezing us for the hours we usually take, I'm wondering what other engineers in my position have found they need to do the work...10 hrs per instrument? 15 hrs per instrument?
I'd love to hear what others have found.
Thanks.
The I&C (Instrumentation and Controls)discipline has lots of little things to worry about, i.e. transmitters, switches, control vavles, etc to specify. For example we might have project with an instrument list that contains 1500 instruments.
With the number of items we keep up with its natural that over time we have calculated the number of hours it takes us to do a project on a hours per instrument basis. We would count an instrument so that a valve is counted as one instrument and not count all the components associated with it- limit switches and solenoid valve, positioners, etc.
With increasing competition squeezing us for the hours we usually take, I'm wondering what other engineers in my position have found they need to do the work...10 hrs per instrument? 15 hrs per instrument?
I'd love to hear what others have found.
Thanks.