Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

EVM question on Status dates for PV and AC

Status
Not open for further replies.

Andrewthill

Electrical
Nov 11, 2009
1
0
0
US
So, I am tracking EVM for a software project. Here is a problem I am facing.Example:

work is for 2 months Nov and Dec.
In November, some of the tasks scheduled for Dec have been completed. This is now reflected in AC.

When I do an EVM visual graph, with a status date for Nov, how do I take the activities completed that were scheduled for Dec? If I change the status date to Dec, then the PV also changes. What I need is an EVM on current status date, with current PV and AC/EV for December tasks that were completed.

Any suggestions?
thanks
Andrew
 
Status
Not open for further replies.
Back
Top