JohnWeal
Mechanical
- Dec 16, 2012
- 124
Good evening,
An EGHEis to be installed in a power plant
The total mass is 2000 kg. It is currently shown installed on directly into the building slab base floor.
I stated that it should be installed on a plinth. (Or two plinths to be more precise - one under each of the two flat bottomed steel saddles)
The manufacturer states in the O&M guidelines to ‘fix one end and the other end fixed but able to float to allow thermal expansion.’ No problem with that. However, with a plinth, I think the floor maybe installed on a slight fall for drainage etc and also the concrete grade may not be as hard.
Just my thoughts as I have not been involved with installing EGHE’s before.
Regards
An EGHEis to be installed in a power plant
The total mass is 2000 kg. It is currently shown installed on directly into the building slab base floor.
I stated that it should be installed on a plinth. (Or two plinths to be more precise - one under each of the two flat bottomed steel saddles)
The manufacturer states in the O&M guidelines to ‘fix one end and the other end fixed but able to float to allow thermal expansion.’ No problem with that. However, with a plinth, I think the floor maybe installed on a slight fall for drainage etc and also the concrete grade may not be as hard.
Just my thoughts as I have not been involved with installing EGHE’s before.
Regards