Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Exhaust Gas Heat Exchanger installation

Status
Not open for further replies.

JohnWeal

Mechanical
Dec 16, 2012
124
Good evening,

An EGHEis to be installed in a power plant

The total mass is 2000 kg. It is currently shown installed on directly into the building slab base floor.

I stated that it should be installed on a plinth. (Or two plinths to be more precise - one under each of the two flat bottomed steel saddles)

The manufacturer states in the O&M guidelines to ‘fix one end and the other end fixed but able to float to allow thermal expansion.’ No problem with that. However, with a plinth, I think the floor maybe installed on a slight fall for drainage etc and also the concrete grade may not be as hard.

Just my thoughts as I have not been involved with installing EGHE’s before.

Regards
 
Replies continue below

Recommended for you

Hello MintJulep,

Sorry, should the heat exchanger be mounted on a plinth or does it not really matter?

Regards
J
 
If the existing slab is "good enough" (i.e. strong enough, level enough) then why would a plinth be needed?

If the existing slab is not good enough (but is known), then a plinth is a possible solution to the deficiencies.

If you can't be sure what the existing slab is then probably cut it out locally at the saddle locations and make a known foundation independent from the slab.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor