structengineer
Structural
- Jun 16, 2005
- 22
Can anyone point me to a place in the code (IBC 2006) that says, if you touch the existing building you need to bring it up to code? The situation I have is that there is an existing building that is block with double tee roof. There appears to be no connections between tee's or tees to the shearwalls. The owner wants to replace some of the tees with planks, add skylights, etc. They just want to be able to walk away without addressing the diaphragm issues. Is there something in the code that address's this situation?