Allan17
Civil/Environmental
- Aug 21, 2007
- 3
The existing lagoon was constructed in 1982 and is currently operational receiving wastewater flows from residential and industrial developments. The lagoon existing containment berms were constructed as compacted clay liners with compaction of 97% or higher standard proctor density. The noted the composition of the berm core is fairly uniform comprised of medium to high plasticity clays.
Since the Lagoon construction the compacted clay liner banks have been eroding and sloughing resulting in vertical faces of up to 1.5m in the most severe locations. The majority of the lagoon banks exhibit vertical faces in the range of approximately 0.5m to 0.75m.
A geotechnical investigation was completed for this lagoon located in northern Alberta. The causes of erosion in his report were stated as follows:
The sloughing affecting the interior side slopes of the storage cell and facultative cell containment berms is believed to be a result of surfacial erosion, in part, by wave action. The exposed faces of the berms in un-armored sideslope areas are comprised of silty clay and clay soils with a fair to poor resistance to erosion. The erosion is exacerbated by periodic/annual drawdown and/or emptying of the cells which: a) eliminates a hydraulic pressure acting as a toe load supporting the side slopes, b) leaves the exposed slopes saturated, heavy and weak, and c) leaves a relatively high residual pore pressure within the clay which is slow to dissipate. The combined affects are resulting in the slumping of the interior slopes. The slumping is resulting in the formation of near vertical faces. This in-turn is developing further instability of the interior sideslopes (in unarmored areas) in the form of tension cracking which, eventually, will lead to further slumping. The slump debris will tend to be washed away by wave action as the cells are once again refilled.
The project requires to rehabilitate the clay lined banks. The first step proposed is to bench 1.4m steps into the existing clay lined berm and rebuild it using clay and recompacting at 150mm lifts to a 3.5:1 sideslope.
The armouring options for the rehabitated sloped surface is where I require additional input. Many option exist for armoring but I am comapring two currently. The first option is riprap which is a tried tested method of erosion control but is very costs in this area since no locally available riprap exists. Contractors are also charging a heavy sum to haul the material in and place it.
The inovative option is to fine grade the slope berm surface with 50mm sand after the surface has been rebuilt to 3.5:1 with compacted clay. The next step is to install 80mil HDPE liner on top of the sand from top of bank to bottom of bank and 5m into the lagoon contstructing an anchor trench at the top of berm and bottom of lagoon floor. The majority of the lagoon floor would be left as compacted clay liner but the banks would be protected with HDPE liner. Can anyone comment on using HDPE as a erosion armoring tool in this application. The HDPE including bank recampaction can be installed for $950,000 where as riprap with compaction is $2,031,750. I am aiming for a solution that works to mitagate errosion and is also cost effective. The storage cell dimmension is 375mx375m and 2.7m depth from top of berm to lagoon bottom. The high water level is 2.2m deep. The lagoon becomes full every 6months and is drained within 3 weeks.
Thanks you in advance for your input. Your help is appreciated.
Allan
Since the Lagoon construction the compacted clay liner banks have been eroding and sloughing resulting in vertical faces of up to 1.5m in the most severe locations. The majority of the lagoon banks exhibit vertical faces in the range of approximately 0.5m to 0.75m.
A geotechnical investigation was completed for this lagoon located in northern Alberta. The causes of erosion in his report were stated as follows:
The sloughing affecting the interior side slopes of the storage cell and facultative cell containment berms is believed to be a result of surfacial erosion, in part, by wave action. The exposed faces of the berms in un-armored sideslope areas are comprised of silty clay and clay soils with a fair to poor resistance to erosion. The erosion is exacerbated by periodic/annual drawdown and/or emptying of the cells which: a) eliminates a hydraulic pressure acting as a toe load supporting the side slopes, b) leaves the exposed slopes saturated, heavy and weak, and c) leaves a relatively high residual pore pressure within the clay which is slow to dissipate. The combined affects are resulting in the slumping of the interior slopes. The slumping is resulting in the formation of near vertical faces. This in-turn is developing further instability of the interior sideslopes (in unarmored areas) in the form of tension cracking which, eventually, will lead to further slumping. The slump debris will tend to be washed away by wave action as the cells are once again refilled.
The project requires to rehabilitate the clay lined banks. The first step proposed is to bench 1.4m steps into the existing clay lined berm and rebuild it using clay and recompacting at 150mm lifts to a 3.5:1 sideslope.
The armouring options for the rehabitated sloped surface is where I require additional input. Many option exist for armoring but I am comapring two currently. The first option is riprap which is a tried tested method of erosion control but is very costs in this area since no locally available riprap exists. Contractors are also charging a heavy sum to haul the material in and place it.
The inovative option is to fine grade the slope berm surface with 50mm sand after the surface has been rebuilt to 3.5:1 with compacted clay. The next step is to install 80mil HDPE liner on top of the sand from top of bank to bottom of bank and 5m into the lagoon contstructing an anchor trench at the top of berm and bottom of lagoon floor. The majority of the lagoon floor would be left as compacted clay liner but the banks would be protected with HDPE liner. Can anyone comment on using HDPE as a erosion armoring tool in this application. The HDPE including bank recampaction can be installed for $950,000 where as riprap with compaction is $2,031,750. I am aiming for a solution that works to mitagate errosion and is also cost effective. The storage cell dimmension is 375mx375m and 2.7m depth from top of berm to lagoon bottom. The high water level is 2.2m deep. The lagoon becomes full every 6months and is drained within 3 weeks.
Thanks you in advance for your input. Your help is appreciated.
Allan