Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

extend drilled piers

Status
Not open for further replies.

rfied112

Structural
Oct 16, 2003
10
have situation with drilled piers installed, rebars extending out to tie into upcoming pile cap ; now realize the top of drilled piers are 4 feet too low. choice is to pour a deeper ( thicker) cap or to " extend" the drilled pier up a few feet. Any thoughts on extending the drilled piers; i.e. lap splice the extended bars into new pier section, does ACi allow extending the pier ?

thanks
 
Replies continue below

Recommended for you

As long as you provide the required lap splice length there should be no problem.
 
How would extending the piers up increase the vertical soil bearing? Or is this a lateral bearing problem?

Mike McCann
MMC Engineering
 
Nevermind. I misread the post.

Mike McCann
MMC Engineering
 
Your extension length is not much greater than the required splice length, assuming #8 or larger rebar. Other than the cost of a bit more concrete, I would make the cap deeper and save the extra step of extending the drilled piers.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor