wXp1223
Petroleum
- Jan 7, 2014
- 3
Hi All,
I have an inqury regarding the weld reject for the process piping during the fabricaton.
Is there any requirement in the ASME B31.3 where if one (1) joint gone through the NDE (RT) has been rejected, another two (2) additional joints shall be selected which is consider a penalty for the rejected joints.
This is the case if the process line only required random NDE.
Appreciate your feedback
I have an inqury regarding the weld reject for the process piping during the fabricaton.
Is there any requirement in the ASME B31.3 where if one (1) joint gone through the NDE (RT) has been rejected, another two (2) additional joints shall be selected which is consider a penalty for the rejected joints.
This is the case if the process line only required random NDE.
Appreciate your feedback