Gourile
Civil/Environmental
- Jan 26, 2001
- 56
It is customary to set extra reinforcing meshes for industrial foundations with depths more than, say, 1.5m(5ft). However only bottom mesh reinforcement in most cases is enough and sometimes even superfluous for carrying the bending moment. Is there any design or practice code to set these extrameshes, sometimes in number of layers, in this type of foundations?