Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations MintJulep on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Fabrication date of pressure vessels 1

Status
Not open for further replies.

etsen

Mechanical
Sep 11, 2006
67
Somebody says the fabrication date of one pressure vessel should be the date when it is completed before inspections of the third part. But I think the date should be the date of final inspection. Take a cellphone for example, the date should be the date when it passes the QA test. So anybody have other points? Standards or codes have rule or definition about the date? Thanks a lot.
 
Replies continue below

Recommended for you

etsen,
The only fabrication date relevant to the pressure vessel is the date of hydrotesting, which must be engraved or visibly displayed in anyway on the nameplate, in accordance with the design code requirements. That will be the recorded date for the "birth" of that particular pressure vessel and will remain the reference date for the life of the vessel. In some places, the other next important date is the vessel registration date with the local government, as applicable. The registration date is considered as the date of beginning of operation, even if in reality the vessel will operate only weeks or few months later, when the plant will start operating.
cheers,
gr2vessels
 
etsen,

Interpretation: Vlll-1-83-317
Subject: Section Vlll-1, “Year Built” in Data Report Forms
Date Issued: October 1, 1984
File: BC84-412

Question: Data Report Forms U-1 through U-4 have an entry to indicate the year in which the vessel or part was built. Does this refer to the year in which the vessel or part was completed, final inspection concluded, and the Data Report signed?

Reply: Yes.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor