etsen
Mechanical
- Sep 11, 2006
- 67
Somebody says the fabrication date of one pressure vessel should be the date when it is completed before inspections of the third part. But I think the date should be the date of final inspection. Take a cellphone for example, the date should be the date when it passes the QA test. So anybody have other points? Standards or codes have rule or definition about the date? Thanks a lot.