Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Fatigue Testing

Status
Not open for further replies.

dansoarr

Mechanical
Sep 15, 2004
18
Hi I'm after some advice

If I have a component that must flex 50 times through its life (2 months), I have an automated test fixture that will flext the component and check for a failure, (true return position).

If I wanted to prove that the component woudl not fail in normal operation say to 1:10,000 at 95%, I belive I'd have to test 30,000 parts to 50 flex's.

Now I only have 10 parts available, although completly representative of the final part.

So can I test each of the 10 parts to 3,000 actuations, and deduce the same fact. i.e

Is it true or fair to say, To test to a failure rate 1:10,000 @ 95%, I could either :-
Test 30,000 components, once each Or
Test 10,000 components, 3 times each Or
Test 1,000 components, 30 times each Or
Test 100 components, 300 times each Or
Test 10 components, 3,000 times each Or
Test 1 component, 30,000 times each ?

Some help would be great.

Thanks

Arron
 
Replies continue below

Recommended for you

Clearly, the last case cannot possibly yield a plausible answer. You could survive 50 car crashes, but you'd be unlikely to survive 30,000 car crashes.

Moreover, since there are a number of long-term and thermal-related issues with fatigue failures that going past 500 actuationson a single unit wouldn't make much sense. Some materials tend to work-harden, so exercising beyond a certain point fundamentally changes the parameters of the material itself, thereby nullifying any potential conclusions. Likewise, mechanical working of a material that can fatigue induces heat, which can accelerate or otherwise alter material behavior as well.


On the other hand, if all pieces can handle 3,000 actuations, then there isn't a problem beyond whether the pieces you have really encompass ALL possible process and material variations.

TTFN

Eng-Tips Policies FAQ731-376


 
What do you mean by "1:10,000 at 95%"? Are you saying you want a 95% confidence that less than 0.001% of the components will fail?

What is the material? If metal, what is the loading vs. yield strength?

ISZ
 
Sounds like you are looking for Mean Time To Failure (MTTF)....
 
Using the true installation loadings, run about ten samples until failure and then do a Weibull analysis and follow it up by applying a 95% confidence limit. From the 95% conf curve, read off the B5 (the point where 5% of the population has failed, with 95% confidence)

Use some Weibull software, it takes away the headaches.


Bill
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor