simonfr
Electrical
- Apr 11, 2005
- 27
We are using the ETAP computer modelling for our power system and are calculating the fault levels for the 600VAC busbars which are connected to the main GTG's
My understanding is that the value always used to determine the fault level is the t – 8ms time, which for a 60Hz sytem is the half cycle time.
Apparently his is the standard for fault calculation studies.
However I am not an expert in this field, and am wondering why a time of t=0 is selected, as would this not be a valid fault level which the boards can ‘see’.
Cheers,
Simon
My understanding is that the value always used to determine the fault level is the t – 8ms time, which for a 60Hz sytem is the half cycle time.
Apparently his is the standard for fault calculation studies.
However I am not an expert in this field, and am wondering why a time of t=0 is selected, as would this not be a valid fault level which the boards can ‘see’.
Cheers,
Simon