Fidic Red book 99: discount to new unit rates

Status
Not open for further replies.

derim01

Structural
Oct 4, 2008
17
0
0
AE
Dear all

During Tender process Contractor provided discount on overall amount of works in BoQ.
In BOq summary contingency is provided 9%.

My question is:
For new unit rates paid according to detailed breakdown submitted (market prices), should we apply discount given to overall sum in Contract BoQ?

Fidic Red Book 99.
 