longisland
Geotechnical
- Sep 25, 1999
- 82
hi,
I need to design an access road to a hill site. The natural is roughly 20 degree;
the approach road gradient has to be reduced to 10 degree.
I can't cut the whole slope down due to site constraint; I plan to reduce the grade by extending the approach up to the mid section of the slope & then trim down the rest of the slope. what is the best approach to construct the approach?
I've thought of constructing a ramp structure or using reinforced earth.
The structure is costly but I'm not confortable filling on existing slope. Any other suggestions?
The existing ground is sandy silt; I'm worry the whole section of the approach may slide if I were to fill earth ontop.
I need to design an access road to a hill site. The natural is roughly 20 degree;
the approach road gradient has to be reduced to 10 degree.
I can't cut the whole slope down due to site constraint; I plan to reduce the grade by extending the approach up to the mid section of the slope & then trim down the rest of the slope. what is the best approach to construct the approach?
I've thought of constructing a ramp structure or using reinforced earth.
The structure is costly but I'm not confortable filling on existing slope. Any other suggestions?
The existing ground is sandy silt; I'm worry the whole section of the approach may slide if I were to fill earth ontop.