stevem1968
Mechanical
- May 16, 2014
- 2
Fire tube Boiler
Total amount of tubes 257
57 Tubes Plugged = 20.8%
What is the ASME or industry standard with regards to the amount of tubes plugged before it becomes unsafe to operate.
Thanks
Steve M
Total amount of tubes 257
57 Tubes Plugged = 20.8%
What is the ASME or industry standard with regards to the amount of tubes plugged before it becomes unsafe to operate.
Thanks
Steve M