chaa
Civil/Environmental
- Jun 8, 2007
- 15
I'm modeling an 11 sq. mile watershed using WinTR-20 for the first time. The drainage area at an existing dam is 6 sq.mile. Approx. 1,500 feet downsream of the dam there is highway crossing A (D.A.=7 sq. miles). Approx. 6,000 feet from highway crossing A there is another crossing, let's call it B (D.A.= 8 sq. miles).
Increasing the storage area at the dam's reservoir, during a 100-year storm event a reduction of approx. 500 cfs of the peak discharge is achieved just downstream of the dam. The model's output shows that the 500 cfs reduction is carried over to crossing A but not to crossing B. At crossing B the peak discharge is approximately the same as in the existing condition (old, smaller reservoir). The schematic developed by the software looks just fine to me. I do not understand why the 500 cfs are not carried over further downstream on the watercourse.
Can anybody help? Where is the problem?
Increasing the storage area at the dam's reservoir, during a 100-year storm event a reduction of approx. 500 cfs of the peak discharge is achieved just downstream of the dam. The model's output shows that the 500 cfs reduction is carried over to crossing A but not to crossing B. At crossing B the peak discharge is approximately the same as in the existing condition (old, smaller reservoir). The schematic developed by the software looks just fine to me. I do not understand why the 500 cfs are not carried over further downstream on the watercourse.
Can anybody help? Where is the problem?