g_pat23
Geotechnical
- Oct 31, 2019
- 3
Hi all,
I have a new residential job that consists of a 1-story slab on grade residence that is to be built on a moderately sloping hillside. My company did three test bores and found the following: Hole 1 consisted of low plasticity clay to approximately 13 feet where weathered but hard limestone bedrock was encountered. The second hole consisted of approximately 7 feet of low plasticity clay underlain with the same limestone bedrock. The third test hole consisted of approximately 2 feet of low plasticity clay underlain by limestone. In order to reach the designed finished floor elevations approximately 2.5 feet, 4.5 feet and, 4.5 feet of cut will have to be performed in the locations of test hole 1, 2, and 3, respectively. My recommendations to them are going to be to perform all their cut earthwork first then in areas where the limestone bedrock is not exposed (specifically along footing lines) dig until the limestone bedrock is reached and backfill with concrete flowable fill to their footing elevations. From there construct footings, etc etc.
Just looking to see what people have to say about this plan/what others experience you all have with flowable fill. Thanks in advance.
I have a new residential job that consists of a 1-story slab on grade residence that is to be built on a moderately sloping hillside. My company did three test bores and found the following: Hole 1 consisted of low plasticity clay to approximately 13 feet where weathered but hard limestone bedrock was encountered. The second hole consisted of approximately 7 feet of low plasticity clay underlain with the same limestone bedrock. The third test hole consisted of approximately 2 feet of low plasticity clay underlain by limestone. In order to reach the designed finished floor elevations approximately 2.5 feet, 4.5 feet and, 4.5 feet of cut will have to be performed in the locations of test hole 1, 2, and 3, respectively. My recommendations to them are going to be to perform all their cut earthwork first then in areas where the limestone bedrock is not exposed (specifically along footing lines) dig until the limestone bedrock is reached and backfill with concrete flowable fill to their footing elevations. From there construct footings, etc etc.
Just looking to see what people have to say about this plan/what others experience you all have with flowable fill. Thanks in advance.