xxpegasus11
Structural
- Nov 29, 2004
- 48
It is proposed to underpin an existing footing in order to add a new floor over an existing single storey by adding a mass concrete footing approx 600mm wide by 600mm high. The soil bearing capacity is well adequate for the proposed loads and size of footing. The contractor proposes to do this in alternate sections of about 4ft long, dry packing each section a day after pouring. Reading through some posts i see theres some debate as to whether each section needs to be tied to adjacent sections through dowels of some sort. Would be grateful for any input on this from anyone whos had experience. Are dowels necessary? If so, what forces would they be designed for? Any other factors from experience/good practice that one should be aware?