jbm4cnc
Mechanical
- May 7, 2012
- 3
thread274-287721
I have a customer with a foundation issue that he does not want to admit.
First off, this machine weighs 45,000 lbs. There is a 12,000 lbs mass on top of it that can move at 18ft/min. The customer was given the spec of 24" of reinforced concrete and 12" of compacting base with a soil bearing of 10T per meter squared. What the contractor did was 6" of #57 stone (did not compact cause he said it was self compacting) and 18" of reinforced concrete. The machine is designed to handle .0001 accuracy positioning. We are finding the moving part of the machine, running parallel to the ground is leaning back over 30 days .0006" and causing the machine not to be square to hold the .0001. Customer says the pad is sufficient to hold tolerances. Yet, we measure floor movement, indicator from old pad and reach over the isolation membrane to new pad, we see floor dip .001". How can i prove to this customer that his contractor didnt do it right. By the way, the civil engineer specified compacted material and 95% proctor (dont know what that means)
Thank you.
I have a customer with a foundation issue that he does not want to admit.
First off, this machine weighs 45,000 lbs. There is a 12,000 lbs mass on top of it that can move at 18ft/min. The customer was given the spec of 24" of reinforced concrete and 12" of compacting base with a soil bearing of 10T per meter squared. What the contractor did was 6" of #57 stone (did not compact cause he said it was self compacting) and 18" of reinforced concrete. The machine is designed to handle .0001 accuracy positioning. We are finding the moving part of the machine, running parallel to the ground is leaning back over 30 days .0006" and causing the machine not to be square to hold the .0001. Customer says the pad is sufficient to hold tolerances. Yet, we measure floor movement, indicator from old pad and reach over the isolation membrane to new pad, we see floor dip .001". How can i prove to this customer that his contractor didnt do it right. By the way, the civil engineer specified compacted material and 95% proctor (dont know what that means)
Thank you.