Hi,
I am doing the structural design for a 2 storey house constructed in a very swampy location. The house is to be constructed out of 8" masonry blocks and 5" thick concrete floor slabs. I have done a few test pits and there is atleast 12 feet of "muck". Bedrock is nowhere to be seen. The site is going to be raised by about 4 feet for flood protection and the ground floor is going to be an additional 3 feet above the fill.
I am currently exploring foundation options and the raft foundation seems like a reasonable solution as opposed to more expensive options such as piling. My question however is whether the 4 feet of fill will be sufficient to distribute the loads so that I don't have any settlement issues considering that the house is heavier than a timber framed structure. If not, what would be a recommended fill layer and how far beyond the building footprint should I extend the fill layer.
Are there other economical foundation options that I can explore?
Thanks
I am doing the structural design for a 2 storey house constructed in a very swampy location. The house is to be constructed out of 8" masonry blocks and 5" thick concrete floor slabs. I have done a few test pits and there is atleast 12 feet of "muck". Bedrock is nowhere to be seen. The site is going to be raised by about 4 feet for flood protection and the ground floor is going to be an additional 3 feet above the fill.
I am currently exploring foundation options and the raft foundation seems like a reasonable solution as opposed to more expensive options such as piling. My question however is whether the 4 feet of fill will be sufficient to distribute the loads so that I don't have any settlement issues considering that the house is heavier than a timber framed structure. If not, what would be a recommended fill layer and how far beyond the building footprint should I extend the fill layer.
Are there other economical foundation options that I can explore?
Thanks