I am in a troubled situation.
1) I have to put a foundation pad
2)The pad is subject to some 20tons uplift
3) I have very little room for it and very little soil mass to rely on
4) Dont want to rely on the soil fill below it, cause no guarantee it will be compacted without damage to neighboring structure.
So I dig into the narrow area and fill with plain concrete and later on cast the pad
QUESTION
1) Is the bond between plain concrete and my later-on-added pad reliable againt 22tons ?
2) IF not, will dowels placed in plain concrete be useful?
3) If not, should I specify some SIKA? (I am not very happy with this alternative though)
4) Whatever my experienced friends recommend.
Respects and Regards
IJR
1) I have to put a foundation pad
2)The pad is subject to some 20tons uplift
3) I have very little room for it and very little soil mass to rely on
4) Dont want to rely on the soil fill below it, cause no guarantee it will be compacted without damage to neighboring structure.
So I dig into the narrow area and fill with plain concrete and later on cast the pad
QUESTION
1) Is the bond between plain concrete and my later-on-added pad reliable againt 22tons ?
2) IF not, will dowels placed in plain concrete be useful?
3) If not, should I specify some SIKA? (I am not very happy with this alternative though)
4) Whatever my experienced friends recommend.
Respects and Regards
IJR