BimEng
Structural
- Jan 9, 2011
- 3
I'm working on a project where we are increasing the size of existing structural columns which fall within walls on multiple floors. The face of the existing column we are increasing was scarified and we dowelled into the top and bottom of the beams which would sit above and below the new columns. A cage was then installed and we also dowelled into the face of the existing column to create a bond between the two.
In order to pour the new section we did a letterbox form so that we could pour above the botton of the existing beam and vibrated well to try and get concrete right up to the underside of the beam. Now that we have removed the formwork we see that there are a number of gaps between the poured column and the existing beam and I'm trying to deterine the best way to repair this.
The gap needs to be filled completely to allow load transfer between the existing beams and the new columns. I am thinking of cleaning out the gap and using a very fluid non-shrink grout to patch these gaps. Any suggestions would be helpful.
In order to pour the new section we did a letterbox form so that we could pour above the botton of the existing beam and vibrated well to try and get concrete right up to the underside of the beam. Now that we have removed the formwork we see that there are a number of gaps between the poured column and the existing beam and I'm trying to deterine the best way to repair this.
The gap needs to be filled completely to allow load transfer between the existing beams and the new columns. I am thinking of cleaning out the gap and using a very fluid non-shrink grout to patch these gaps. Any suggestions would be helpful.