Cleron
Industrial
- Jan 17, 2004
- 3
Hello,
I just found this site and I hope I can get a little guidance on a personal project now in progress.
I am building a detatched garage. So far the site is prepared for the concrete floor/slab. The building will be 30 ft. deep X 40 ft. wide. We have had to build concrete walls to contain the floor. We filled with a slate mixture and tamped each load with the bulldozer. The top few inches is crusher-run and smoothed as close as possible to insure an even concrete thickness. The top of the walls (back wall and 1 side) have metal rods extending out a few inches for the concrete floor to be poured over. I have asked for a 5" floor thickness and would really like to have this done without expansion joints. In other words, a smooth continuous floor. The contractor is currently going to use the fiber filled concrete mixture instead of metal reinforcemnet. I have had some experience with this on outside concrete but would this be any problem with an interior floor?
(1)-Am I asking too much to try and get a smooth (30 X 40)floor without joints? I do know in my industrial experience we poured floors up to 50 ft. X 100 ft. without joints or metal reinforcement. But that concrete was 10" or more thick and 5000 lb.
(2)-Will 3000 lb. concrete be enough or should I specify 4000?
(3)-The slab will be over a vapor barrier.
(4)-The floor will be poured on top of the back and one end wall and poured against forms near grade for the other end and front.
(5)-I'm not sure yet but in the near future I might use either an epoxy finish or other type of floor finish. Of course I must wait for a minimum 30 days cure before attempting any of these. Is that amount of time sufficient?
Thanks for your input.
I just found this site and I hope I can get a little guidance on a personal project now in progress.
I am building a detatched garage. So far the site is prepared for the concrete floor/slab. The building will be 30 ft. deep X 40 ft. wide. We have had to build concrete walls to contain the floor. We filled with a slate mixture and tamped each load with the bulldozer. The top few inches is crusher-run and smoothed as close as possible to insure an even concrete thickness. The top of the walls (back wall and 1 side) have metal rods extending out a few inches for the concrete floor to be poured over. I have asked for a 5" floor thickness and would really like to have this done without expansion joints. In other words, a smooth continuous floor. The contractor is currently going to use the fiber filled concrete mixture instead of metal reinforcemnet. I have had some experience with this on outside concrete but would this be any problem with an interior floor?
(1)-Am I asking too much to try and get a smooth (30 X 40)floor without joints? I do know in my industrial experience we poured floors up to 50 ft. X 100 ft. without joints or metal reinforcement. But that concrete was 10" or more thick and 5000 lb.
(2)-Will 3000 lb. concrete be enough or should I specify 4000?
(3)-The slab will be over a vapor barrier.
(4)-The floor will be poured on top of the back and one end wall and poured against forms near grade for the other end and front.
(5)-I'm not sure yet but in the near future I might use either an epoxy finish or other type of floor finish. Of course I must wait for a minimum 30 days cure before attempting any of these. Is that amount of time sufficient?
Thanks for your input.