RRaghunath
Electrical
- Aug 19, 2002
- 1,729
Normally, the loading ramp for GTGs is stipulated by the manufacturers, such as 20 minutes from no load to full load.
My doubt is when a machine is functioning as "Spinning Reserve" in the power system, the machine is expected to pick up load pretty quick in case of tripping of one of the loaded generators (otherwise the grid may be in jeopardy) and with ramp rate stipulation as above, how is this achieved?
Could some one throw light on the subject. Thanks in anticipation.
My doubt is when a machine is functioning as "Spinning Reserve" in the power system, the machine is expected to pick up load pretty quick in case of tripping of one of the loaded generators (otherwise the grid may be in jeopardy) and with ramp rate stipulation as above, how is this achieved?
Could some one throw light on the subject. Thanks in anticipation.