Kaspen
Civil/Environmental
- Sep 11, 2023
- 3
All, currently constructing a building that the construction team does not feel comfortable with the SE foundation design. The building is designed with 2' diameter 66' deep drilled caisson utilizing skin friction no bedrock was encountered. The soils are soft to medium stiff clay. Concrete grade beams placed from caissons to caisson with the slab being monolithic placed with the grade beams. The building is an energy plant supporting multiple cooling towers on the roof and chillers with up to 24" diameter piping supported from the cast in place roof deck. The average span between the 20 drilled caisson is 15' up to 27' apart. During a meeting the SE informed the team the soil below the grade beams need to support 1500 psf. Is this common to use grade beams as spread footings and skin friction from drilled caisson?