A couple of days ago we had a failure of a GE 1000 hp extruder motor on one of our films lines here in our plant. The motor had a lot of water and ice ingested into the air intake from the roof during the snow storm shorting out 2 of the 6 motor field windings.
The motor shop says the repairs will take a few weeks mainly because of the fact that the motor has pole face windings and the repairs are labor intensive. I was wondering if anyone has experience with pole face winding repairs and if there might be a way to speed up the process. I don't think the shop is sandbagging on this one but I would like to make sure anyway. I have been told that getting the coils from GE will take 4 to 6 months. I don't have a contact at GE so I can't confirm this right away.
We have installed an 800 hp motor and will run it until the 1000 hp motor gets back from the shop. The main problem with this is we may have to derate production output on some products with the smaller motor in place.
Thanks
Wayne
The motor shop says the repairs will take a few weeks mainly because of the fact that the motor has pole face windings and the repairs are labor intensive. I was wondering if anyone has experience with pole face winding repairs and if there might be a way to speed up the process. I don't think the shop is sandbagging on this one but I would like to make sure anyway. I have been told that getting the coils from GE will take 4 to 6 months. I don't have a contact at GE so I can't confirm this right away.
We have installed an 800 hp motor and will run it until the 1000 hp motor gets back from the shop. The main problem with this is we may have to derate production output on some products with the smaller motor in place.
Thanks
Wayne