bookowski
Structural
- Aug 29, 2010
- 983
Being lazy here, I have not looked into this much yet but it's a construction issue so in the interest of time I am hoping someone with experience in the design of these walls can give a gut level opinion here before I dive in.
I've got a small new building (1 story steel frame) adjacent to an existing keystone retaining wall. The wall is 11' tall from t.o. wall to grade. Our proposed footing is down 5' from grade, so 7' above the b.o. wall and is offset 10' from the b.o. retaining wall (that's to the edge of our footing). So I've got a line at 10H:7V from b.o. wall to b.o. footing. We have the original wall design drawings (it's relatively new) and the fabric is specified just under 10ft, so just outboard of our proposed footing. These details were missed during the initial design and if I had caught this I would have pushed the footing deeper, but now i'm stuck doing it during excavation and trying to minimize how much yelling I have to endure. The contractor/owner side are pushing that it's fine but I did not agree.
I was able to contact the original designer. He worked for the wall company and is now retired but we've had a few back/forth emails. His suggestion was to push the footing down all the way to the adjacent grade, i.e. b.o. footing 11ft down. This seems excessive but I am not familar with the design of these walls. From our emails I am getting the impression that his design is likely prescriptive or based on some rules of thumb (i.e. "fabric went back 10ft because it's about a 10ft tall wall"). Now that I've got him in the loop I don't want to ignore his suggestion.
My 2nd concern is that if they do dig down to the full depth, 11ft, right off the face of the fabric this seems likely to disturb the reinforced soil. Short of driving piles or some other support of excavation I don't see how that won't become a mess. The could pile support that side of the building but I'm hoping to avoid that.
I've got a small new building (1 story steel frame) adjacent to an existing keystone retaining wall. The wall is 11' tall from t.o. wall to grade. Our proposed footing is down 5' from grade, so 7' above the b.o. wall and is offset 10' from the b.o. retaining wall (that's to the edge of our footing). So I've got a line at 10H:7V from b.o. wall to b.o. footing. We have the original wall design drawings (it's relatively new) and the fabric is specified just under 10ft, so just outboard of our proposed footing. These details were missed during the initial design and if I had caught this I would have pushed the footing deeper, but now i'm stuck doing it during excavation and trying to minimize how much yelling I have to endure. The contractor/owner side are pushing that it's fine but I did not agree.
I was able to contact the original designer. He worked for the wall company and is now retired but we've had a few back/forth emails. His suggestion was to push the footing down all the way to the adjacent grade, i.e. b.o. footing 11ft down. This seems excessive but I am not familar with the design of these walls. From our emails I am getting the impression that his design is likely prescriptive or based on some rules of thumb (i.e. "fabric went back 10ft because it's about a 10ft tall wall"). Now that I've got him in the loop I don't want to ignore his suggestion.
My 2nd concern is that if they do dig down to the full depth, 11ft, right off the face of the fabric this seems likely to disturb the reinforced soil. Short of driving piles or some other support of excavation I don't see how that won't become a mess. The could pile support that side of the building but I'm hoping to avoid that.