Pongsagon
Mechanical
- Jul 11, 2007
- 12
Gentleman,
There is existing underground onshore natural gas pipeline size 34", API 5L X65, lenght 1.3 km. New pipeline size 20" will be tied-in to this existing pipeline by cutting and install tee reducer, 30"X20". Could you please advise as follows;
1) The Contractor has proposed to perform golden weld at tie-in point(34"-2 joints), hydrotest will be waived. Is this propose acceptable and comply to code (should be ASME B31.8), which article?
2) What is golden weld?
3) Is there any other codes concern to this job i.e. ASME section IV, please advise.
Thanks in advance.
There is existing underground onshore natural gas pipeline size 34", API 5L X65, lenght 1.3 km. New pipeline size 20" will be tied-in to this existing pipeline by cutting and install tee reducer, 30"X20". Could you please advise as follows;
1) The Contractor has proposed to perform golden weld at tie-in point(34"-2 joints), hydrotest will be waived. Is this propose acceptable and comply to code (should be ASME B31.8), which article?
2) What is golden weld?
3) Is there any other codes concern to this job i.e. ASME section IV, please advise.
Thanks in advance.