Gordon,
The 3/2 start requirements comes from the API standards specific for the oil and gas industry. If you are interested i will find out the actual references. these standards outline the requirement for the compressors and and pumps being driven - and probably based on the old saying time is money!!
G
The 3/2 start requirements comes from the API standards specific for the oil and gas industry. If you are interested i will find out the actual references. these standards outline the requirement for the compressors and and pumps being driven - and probably based on the old saying time is money!!