Hi all. I have an existing piping & pump process system but will be updated to new design. There is a specification which states that “The HP mud pumps shall be located to allow gravity feed from mud tanks in case of failure of super charge pumps. Supercharge pumps shall have gravity feed bypassing piping”
The present design supercharge pumps are based on 3x100% to supply 3x100% HP mud pumps. From the 4 mud tanks. The inlet manifold to supercharge pumps is located on the same main header from the tanks. Discharge from supercharge pumps goes to the respective HP mud pumps. Should one of the supercharge pumps fail there is a bypass line from the tanks to the discharge of the supercharge pump, but the bypass can not guarantee the required NPSr to the HP mud pumps.
If there was a crossover on the discharge of the supercharge pumps there would not be a need for the gravity feed from the mud tanks. Is that acceptable?
Additionally is there aneed to have 3 supercharge pumps if we can get away with just 2?
The present design supercharge pumps are based on 3x100% to supply 3x100% HP mud pumps. From the 4 mud tanks. The inlet manifold to supercharge pumps is located on the same main header from the tanks. Discharge from supercharge pumps goes to the respective HP mud pumps. Should one of the supercharge pumps fail there is a bypass line from the tanks to the discharge of the supercharge pump, but the bypass can not guarantee the required NPSr to the HP mud pumps.
If there was a crossover on the discharge of the supercharge pumps there would not be a need for the gravity feed from the mud tanks. Is that acceptable?
Additionally is there aneed to have 3 supercharge pumps if we can get away with just 2?