I have the following situation:
We have ordered a vessel to an italian manufacturer which during the manufacturing DID NOT GROUND FLUSHED the longitudinal welds before welding over them the reinforcing rings and some plates for platforms fixing.
I told them that this is not acceptable so they proposed me
to accept the situation considering that "we have done on internal side, after flush-grinding of barrel's longitudinal welding, Ultrasonic Test the interested area and no defects have been found".
Please I need a very strong support (something from ASME 8 or 9) in order to accept or reject their proposal. Any advise is welcome.
Thank you very much.
We have ordered a vessel to an italian manufacturer which during the manufacturing DID NOT GROUND FLUSHED the longitudinal welds before welding over them the reinforcing rings and some plates for platforms fixing.
I told them that this is not acceptable so they proposed me
to accept the situation considering that "we have done on internal side, after flush-grinding of barrel's longitudinal welding, Ultrasonic Test the interested area and no defects have been found".
Please I need a very strong support (something from ASME 8 or 9) in order to accept or reject their proposal. Any advise is welcome.
Thank you very much.