Is it standard practice to ground both side rails of aluminum cable tray at support locations? I am designing cable tray that is carrying control cables from a new sub over to an old sub where there is an existing control house with available panel space. The cable tray is run vertically up to 25' from the new yard, over, and down into the old yard on custom steel structures.