Dennis59
Structural
- Dec 29, 2000
- 56
Hello all,
I couldn't think of a better title for this post - sorry.
Here's the scenario: You're a consulting engineer - hired to issue plans and specs for a project. A geotechnical investigation is undertaken and the geotech firm drills some borings. They find groundwater several feet ~above~ your planned bottom of building. (Assume that the building will be waterproofed and designed to resist buoyancy - that's not at issue for my question.)
What is your responsibility now in terms of providing information for the Contractor who will eventually win the bid and have to dewater and dig the hole?
Assume that the building you are designing is pretty much in the middle of nowhere - there are no issues with sensitive adjacent buildings and there are no significant issues with finding a place to get rid of the pumped-out groundwater.
Would you, as the consulting engineer, order some kind of additional tests at this point (during the preparation of plans and specs) to determine just how much water might be down there, and how difficult the dewatering might be? For example, might you order that a test well be installed and pumped in order to see what the water level does in some nearby boring that has ~not~ been backfilled with cuttings and/or grouted full? (It is my experience that soil borings are backfilled almost immediately, so the driller would have to be instructed in advance to install piezometers in at least a few water-containing bore holes.)
Or would you just include the geotech report in the plans and specs and let the potential contractors figure out what to do about dewatering?
It is my experience that Owners are reluctant to even do enough soil borings to figure out bearing capacity/settlement - much less install a test well. What is your experience?
If no test well is installed in advance, what happens when the construction starts and it turns out that there is so much water that 'conventional dewatering' is ineffectual? Would this typically be considered a "changed condition" (read "more $$") even if the groundwater level is exactly where the soil borings said it would be, and the subgrade is the same type of soil as the borings indicated? If so, at what point does it become a "changed condition"?
Do contractors (or dewatering subcontractors) ever go to a job site in advance of submitting a bid and do their own tests (on their own nickel)? I have heard tales of this, but have never actually seen it myself...
If there is a 'standard of care' with respect to this issue, I would like to know what it is so I can attempt to abide by it.
Thanks for reading, and for any response you care to offer.
I couldn't think of a better title for this post - sorry.
Here's the scenario: You're a consulting engineer - hired to issue plans and specs for a project. A geotechnical investigation is undertaken and the geotech firm drills some borings. They find groundwater several feet ~above~ your planned bottom of building. (Assume that the building will be waterproofed and designed to resist buoyancy - that's not at issue for my question.)
What is your responsibility now in terms of providing information for the Contractor who will eventually win the bid and have to dewater and dig the hole?
Assume that the building you are designing is pretty much in the middle of nowhere - there are no issues with sensitive adjacent buildings and there are no significant issues with finding a place to get rid of the pumped-out groundwater.
Would you, as the consulting engineer, order some kind of additional tests at this point (during the preparation of plans and specs) to determine just how much water might be down there, and how difficult the dewatering might be? For example, might you order that a test well be installed and pumped in order to see what the water level does in some nearby boring that has ~not~ been backfilled with cuttings and/or grouted full? (It is my experience that soil borings are backfilled almost immediately, so the driller would have to be instructed in advance to install piezometers in at least a few water-containing bore holes.)
Or would you just include the geotech report in the plans and specs and let the potential contractors figure out what to do about dewatering?
It is my experience that Owners are reluctant to even do enough soil borings to figure out bearing capacity/settlement - much less install a test well. What is your experience?
If no test well is installed in advance, what happens when the construction starts and it turns out that there is so much water that 'conventional dewatering' is ineffectual? Would this typically be considered a "changed condition" (read "more $$") even if the groundwater level is exactly where the soil borings said it would be, and the subgrade is the same type of soil as the borings indicated? If so, at what point does it become a "changed condition"?
Do contractors (or dewatering subcontractors) ever go to a job site in advance of submitting a bid and do their own tests (on their own nickel)? I have heard tales of this, but have never actually seen it myself...
If there is a 'standard of care' with respect to this issue, I would like to know what it is so I can attempt to abide by it.
Thanks for reading, and for any response you care to offer.