Skip517
Structural
- Jun 22, 2007
- 4
I have a job where the concrete contractor installed the steel bearing plates out of level. Please see the attached picture. The concrete pier below is 12"x24" the beam is sitting on the pier in the length direction (24") There is a steel bearing plate cast into the concrete. The beam is supposed to be welded to the bearing plate. (The anchors shown are only weld on threaded anchors for erection only.)I was thinking of using a series of plates to complete the shimming process, but in some cases the plate is out of level in both directions, so the plate thicknesses would vary on each side of the flange. After the shimming process, does anyone have any ideas on a grout to use to fill the gaps. Standard non-shrink grout (under a column base plate type) would be difficult to get into the voids. I am open to any other repair ideas also.
Thanks.
Thanks.