Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations IDS on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Grouting top course of CMU wall with

Nythius

Structural
Sep 22, 2024
3
This feels like a stupid question, but after extensive googling and searching these forums I still don't have an answer...

New nonloadbearing CMU wall going to underside of existing slab (or any structure for that matter). Slight gap for deflection of course. Partially grouted with bond beams and verts. My question is what is the best detail at the top... how do you get grout into the top course?

Below is what I've come up with:
-bond beam at second course from top
-verts stop at top of second course (so you can "drop the blocks over rebar")
-grout fill with top course not in place
-wet-set little 16" dowels so you have at least something extending to top course
-then install top course (need to cut slots in face to slide it in with rebar already there...)
-drypack the cells with verts in the top course
-install "retainer angles" for out-of-plane restraint

see attached screenshot.

Alright...fire away...prove I'm an idiot.

Thanks in advance,
 

Attachments

  • top of masonry wall.png
    top of masonry wall.png
    79.5 KB · Views: 19
Replies continue below

Recommended for you

If I asked one of the masons I usually work with they'd probably say they'll just cut a slot in face of the block and push the blocks on that way.
 
They make open ended blocks for these purposes (i.e., so you don't have to lower every block from the top of the vertical rebars). In this case the correct blocks to use are open ended bond beam blocks (i.e., with a short web at the center of the 2 cells), but masons, can get creative with saws/chisels/hammers to use regular blocks if that is all they have access to.

As far as grouting, face shells will be removed and formed up with wood/etc. as needed to get grout into the top course.
 
If you are going to remove the face shells, why buy an open end bond beam block?
 
If you are going to remove the face shells, why buy an open end bond beam block?
Good question. I guess you might as well not. Then again, if you had a stack of them laying there you might use them and only knock out face shells where you thought you needed to. As I think about the referenced detail more, the most troublesome part seems to me like it would be getting the bond beam horizontal rebar into the top course below an existing elevated slab. How would this typically be done? Removing face shells? All of them? I think you could form and pour the entire bond beam instead of using CMU. I have seen the referenced detail on drawings often. There must be a typical procedure used by masons, or is it always modified/substituted via RFI or without asking. Maybe a CMU guru will chime in.
 
I suppose you could install the bond beam one course down if you even need one
 
Thanks all. Good to know about the open ended blocks.

Without them, I guess it's not such a big deal to knock them out on site...it's only 10'x13' tall wall. I had instinctively tried to avoid the need for widespread manual modifications to the blocks, but maybe that is easier than dropping the blocks over the bar for the top ~4'.

I still think I am missing something....people build miles of these walls in their parkades to enclose service rooms etc. I have seen details that show the bond beam at the top with no explanation as to it works... and they are not coring/sleeving the slab, as I would have noticed that.

Guess I'll just have to swallow my pride and ask a mason next time I see one....
 
Thanks all. Good to know about the open ended blocks.

Without them, I guess it's not such a big deal to knock them out on site...it's only 10'x13' tall wall. I had instinctively tried to avoid the need for widespread manual modifications to the blocks, but maybe that is easier than dropping the blocks over the bar for the top ~4'.

I still think I am missing something....people build miles of these walls in their parkades to enclose service rooms etc. I have seen details that show the bond beam at the top with no explanation as to it works... and they are not coring/sleeving the slab, as I would have noticed that.

Guess I'll just have to swallow my pride and ask a mason next time I see one....
My guess is some combination of knockout blocks and them making enough openings in the faces to get it all in place. Definitely best to ask a mason tho.
 

Part and Inventory Search

Sponsor