nhcf
Electrical
- Oct 22, 2014
- 74
Facility has (2) 4160 VAC synchronous generators each tied to 5KV bus through individual generator breakers. 5 KV bus is tied to LV connection of GSU transformer. HV of GSU transformer feeds 15 KV breaker and connects to utility.
Does this GSU fall under the requirements of NEC? If so how are the requirements of 450.3(A) transformer overcurrent protection applied? I assumed the LV is the 'primary' - why isn't a dedicated OCPD required on the LV side of the transformer?
Does this GSU fall under the requirements of NEC? If so how are the requirements of 450.3(A) transformer overcurrent protection applied? I assumed the LV is the 'primary' - why isn't a dedicated OCPD required on the LV side of the transformer?