jamoca67
Geotechnical
- Oct 9, 2015
- 2
I'm working on a site that has used 12 x 53 steel H piles for end bearing piles. I'd like to use these piles again (Grade 50), but I also need the pile for lateral capacity purposes. I'd like to embed the pile a minimum of 1 ft into a shale grading highly to moderately weathered, +/- 5,000 psi unconfined strength. I need this embedment because the soils above the rock are pretty crappy. I'm planning to use pile points, and I'll be specifying a wave equation analysis prior to the start of work for the Contractor.
I was thinking of writing the spec so that it gives a minimum penetration requirement into the shale, and let the contractor figure out how to do it. Maybe, require the Contractor to submit a pile driving plan with contingencies should they be unable to get 1 foot of penetration with an impact hammer.
Does anyone see any issues with this approach? Thank you for your time.
I was thinking of writing the spec so that it gives a minimum penetration requirement into the shale, and let the contractor figure out how to do it. Maybe, require the Contractor to submit a pile driving plan with contingencies should they be unable to get 1 foot of penetration with an impact hammer.
Does anyone see any issues with this approach? Thank you for your time.