I have typically specified the connection of steel H piles to pile caps to be 6" embedment. The question that has always stuck in my mind is: How does one analyze the connection? A quick check of the bearing of the concrete on the area of steel alone typically gives a stress that exceeds the allowable bearing stress of the concrete? Thoughts???