Have task 7 day lag before another task

Status
Not open for further replies.

looknow12

Civil/Environmental
Oct 5, 2011
1
I'm using Primavera P3. I have one central task with predecessors and successors and which will shift throughout the project.

I need to create a task which will always be 7 days before the start of this other task.

I have tried a SS and SF with a -7D lag. But it does not seem to work (the date of this new task does not seem to automatically calc 7 days prior)
 
Replies continue below

Recommended for you

Is the "task which will always be 7 days before the start of this other task" a milestone or an activity?
Does it require resources?
Does it have a variable duration?