sjohns4
Civil/Environmental
- Sep 14, 2006
- 123
A municipality I'm working with to design a developer funded system is requiring a casing to be drilled under a creek then a carrier pipe to be slid through, both HDPE.
I've had many HDPE pipelines installed by HDD method, but never did a casing / carrier - it just seems overkill to me.
However, before I try to argue the point that it's overkill I'd like to hear opnions from some others in the industry. Has anyone seen a fusible joint pipe fail after passing the inital pressure test?
Thanks,
Mike
I've had many HDPE pipelines installed by HDD method, but never did a casing / carrier - it just seems overkill to me.
However, before I try to argue the point that it's overkill I'd like to hear opnions from some others in the industry. Has anyone seen a fusible joint pipe fail after passing the inital pressure test?
Thanks,
Mike