WastewaterM
Civil/Environmental
- Mar 11, 2014
- 2
Hi everyone!
New guy here though I’ve lurked quite a bit. I have a couple of questions that have been bothering me a bit regarding pump/system curves in a parallel pumping set-up and came across this old thread ( - numbered as thread407-245347) in my search for answers. JJPellin did a great job on directly answering one of them—how to appropriately calculate the NPSH of a system when you have variable flows/number of pumps running in a set-up, but I do have one thing that I’d like to clear up and would appreciate if someone is able to provide an answer. Unfortunately it doesn’t appear that I’m able to reply directly to that thread anymore, so I’ve started a new one.
Say you have the same set-up as in the old linked thread--parallel two-pump set-up with common suction and discharge piping lengths and short individual suction/discharge suctions leading into/out of the pumps. How do you treat the losses in the common suction section? Let’s also say that at our 2 pump flow we have 1,000 gpm through the system as our design point with each pump contributing 500 gpm. I’ve have a spreadsheet that created a system curve based on just the common discharge headlosses that was based on the total flow through the system, and the same spreadsheet calculated the minor/individual losses by adding the losses experienced at 500 gpm through the remaining sections of pipe. This makes sense to me to do for the individual sections leading into/out of the pump, but what about for the common suction section? Should a flow rate of 1,000 gpm been used instead and the losses added to the system curve instead of being treated as individual losses? Is it possible to work this either way?
Thanks for any input!
New guy here though I’ve lurked quite a bit. I have a couple of questions that have been bothering me a bit regarding pump/system curves in a parallel pumping set-up and came across this old thread ( - numbered as thread407-245347) in my search for answers. JJPellin did a great job on directly answering one of them—how to appropriately calculate the NPSH of a system when you have variable flows/number of pumps running in a set-up, but I do have one thing that I’d like to clear up and would appreciate if someone is able to provide an answer. Unfortunately it doesn’t appear that I’m able to reply directly to that thread anymore, so I’ve started a new one.
Say you have the same set-up as in the old linked thread--parallel two-pump set-up with common suction and discharge piping lengths and short individual suction/discharge suctions leading into/out of the pumps. How do you treat the losses in the common suction section? Let’s also say that at our 2 pump flow we have 1,000 gpm through the system as our design point with each pump contributing 500 gpm. I’ve have a spreadsheet that created a system curve based on just the common discharge headlosses that was based on the total flow through the system, and the same spreadsheet calculated the minor/individual losses by adding the losses experienced at 500 gpm through the remaining sections of pipe. This makes sense to me to do for the individual sections leading into/out of the pump, but what about for the common suction section? Should a flow rate of 1,000 gpm been used instead and the losses added to the system curve instead of being treated as individual losses? Is it possible to work this either way?
Thanks for any input!