norzul
Mechanical
- Dec 1, 2005
- 99
Hi,
We just procured 4 HRSGs for our cogen project. It has supplementary firing (SF) capabilities. Without firing the production is about 50 ton/hr. With SF, 95 t/h. The ramping rate is 15 ton/hr per minute. Is this quite typical for this size of HRSG?
I've checked our existing boilers (MCR=105 ton/hr), the ramping rate is 20 ton/hr per minute. Puzzle me, coz all the while I thought the ramp rate for HRSG should be higher than the conventional boiler..???
Any advise?
Thanks
norzul
We just procured 4 HRSGs for our cogen project. It has supplementary firing (SF) capabilities. Without firing the production is about 50 ton/hr. With SF, 95 t/h. The ramping rate is 15 ton/hr per minute. Is this quite typical for this size of HRSG?
I've checked our existing boilers (MCR=105 ton/hr), the ramping rate is 20 ton/hr per minute. Puzzle me, coz all the while I thought the ramp rate for HRSG should be higher than the conventional boiler..???
Any advise?
Thanks
norzul