Abu Bakar
Petroleum
- Dec 5, 2018
- 5
Hi, kind of stuck with the ASME 31.3 requirement here.
In ASME 31.3, there is no clear definition on how much is the pressure rating for the line to be considered as high/low pressure. The closest statement I can found is, the definition of high/low pressure line will be based on owner definition (ie the party that's doing the design)-excerpt as in photo attached.
- CHAPTER IX K300 High Pressure Piping
Now, in the case of high-pressure line is defined by owner, the rule in CHAPTER IX should be applied.
ASME 31.3 mentioned there's exemption for mandatory heat treatment, if condition stated in table 331.1.3 is satisfied (as in picture attached)
- CHAPTER V 331 Heat Treatment
If we consider the line is high pressure, and we are following the rule in CHAPTER IX, it stated that the exemption for mandatory heat treatment as stated in table 331.1.3 will be voided if the thickness exceeds 19mm.
CHAPTER IX K331 Heat Treatment
Now my confusion is, correct me if I am wrong, my understanding is if we are following rule in CHAPTER IX, all P1 to P1 Weld will need to be heat treated when the thickness exceed 19mm, and the exemption can only be applied to the line with less than 19mm thickness.
In ASME 31.3, there is no clear definition on how much is the pressure rating for the line to be considered as high/low pressure. The closest statement I can found is, the definition of high/low pressure line will be based on owner definition (ie the party that's doing the design)-excerpt as in photo attached.
Now, in the case of high-pressure line is defined by owner, the rule in CHAPTER IX should be applied.
ASME 31.3 mentioned there's exemption for mandatory heat treatment, if condition stated in table 331.1.3 is satisfied (as in picture attached)
If we consider the line is high pressure, and we are following the rule in CHAPTER IX, it stated that the exemption for mandatory heat treatment as stated in table 331.1.3 will be voided if the thickness exceeds 19mm.
Now my confusion is, correct me if I am wrong, my understanding is if we are following rule in CHAPTER IX, all P1 to P1 Weld will need to be heat treated when the thickness exceed 19mm, and the exemption can only be applied to the line with less than 19mm thickness.