Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations IDS on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

HEC-HMS

Status
Not open for further replies.

larryTHUR

Civil/Environmental
Jan 10, 2012
7
Hello,

one question again. I'm working on my first project with HEC-HMS. I got a example, but i want to understand what i'm done.
For a subbasin, you can choose the Baseflow Method Recession, like in my example. After this you have to enter a recession constant. Where can i get this figure or how i can compute this. I try it with google, but i'm from Germany and i didn't find a similar word.
The other possibility is, that i say, it's is only one rain event and the area is very small, so i don't need the baseflow.

thankful

larryTHUR
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor