Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations GregLocock on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

HEC-RAS Channel "forcing"

Status
Not open for further replies.

DMcGrath

Civil/Environmental
Feb 5, 2003
194
I have a project where the first 6 or so cross sections have a parallel channel configuration. The channel with the higher invert is the "main" channel and the lower channel is where the overflow will go. Can I force the program to start the flow in the upper channel section, then overflow into the lower? As it runs now, it starts with the flow in the lower channel and the upper channel has zero flow. The upper channel is the designated discharge for a large pond, so I know the water will at least start there.
 
Replies continue below

Recommended for you

Yes, you can "force" the program to start in the upper channel and set it so that it only leaves that channel if the channel becomes submerged. There is an option in the cross-sections input box, under the Options menu, for setting ineffective flow areas. You want to set temporary ones, that disappear when the elevation is breached.

This link is probably more articulate.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor